Timeline Communication QA1
Q: What is the timeline/schedule for this proposal? 10-19
A:The board of selectmen will be meeting to discuss the proposal during their November 5th meeting. If they approve the project, it is moved to the Board of Finance, who will begin deliberations during their November 14th board meeting. If the BOF approves the project for referendum, it will move to a town vote in early Spring 2019. It is important to note that a town meeting must be held 45 days in advance of actually scheduling a referendum. If approved in referendum, the town would submit an application for a state grant by June 30, 2019. Pending approval of state funding in Spring 2020, the project would go out to bid by Fall 2020, with occupancy anticipated by Fall 2022.